目录
一、试验段选择及工程概况·················3
1、试验段选择·····················3
2、工程概况······················3
3、主要工程数量····················3
4、试验范围······················3
二、工艺试验目的·····················3
三、编制依据·······················4
四、填料要求及来源····················4
六、试验段的目的及准备··················4
七、施工工艺·······················5
1、施工工艺流程图···················6
2、施工工艺说明····················6
3、注意事项······················8
八、施工人员、机具准备··················8
1、人员准备······················8
2、施工机具准备····················8
3、主要施工人员及机械一览表··············8
九、工期安排·······················9
十、附件························10
十一、质量保证措施····················11
1、质量保证体系和措施·················11
2、质量工艺措施····················12
十二、安全保证措施····················12
1、建立安全保证体系和教育、组织············12
1
2、安全技术措施····················13
十三、配合试验段施工总结出施工组织管理经验········13
1、组织管理工作措施··················13
2、优化机械设备····················13
3、改善作业条件、文明有序组织施工···········14
4、技术保证措施····················14
十四、文明施工和环保、水土保持措施············14
1、机具、材料管理···················14
2、施工环境、水土管理·················15
3、水土保持措施····················17
十五.附表························18
2
路基试验段方案
一、试验段选择及工程概况
1、试验段选择
根据施工现场地基处理情况,路基本体填筑工艺性试验段选择在YK71+140~
YK71+340段,长200m。本段路基位于南靖县丰田镇南坪村境内,该段最大填土高度
为8.6m,符合试验段位置选择的要求。
2、工程概况
试验段位于主线区间路基内,大部分处在香蕉林地带,地形相
文档评论(0)